Minutes of the forward endcap EMC meeting, 12th of December 2022, 14:00-14:15

Cosmics Test Station Bonn:

  • Bonn test station: trouble with failing channels (overflow), need to be looked at

SADC Power Supplies:

  • Need to change components on PCBs (already done for the units we have in Bochum)
  • Some changes to backplane PCB necessary (coil to measure current)
  • 6-SADC-backplane redesigned, 15-SADC-backplane waiting for redesign