Minutes of the Forward Endcap EMC Meeting, 25th of July 2022, 14:00-14:15

Submodule Transport:

  • Delivery of next five submodules: August 4.
  • 4 more 5-submodule deliveries possible, however not in a regular weekly term due to limited capacity of Fahrdienst/RUB.

Cabling:

  • Cross talk in signal cable pitch-adapter: Mitigated by new design with larger signal route distances (tests outstanding yet)

-- ThomasHeld - 25 Jul 2022