Minutes of the forward endcap EMC eZuce SRN meeting, 8th of October 2018, 14:00-14:20

Presence:

  • Basel: -
  • Bochum: Fritz-Herbert, Cathrina, Claudius, Fritz-Herbert, Malte, Matthias, Tobias H., Tobias T., Tom
  • Bonn: Christoph, Ulrike
  • Groningen: Myroslav
  • Stockholm: -
  • Uppsala: -
  • Giessen: Markus
  • GSI: -

VPTT Submodule Production:

  • Production is running smoothly at a rate of 5 modules a week
  • Bonn is going on with cosmics test measurements of delivered submodules
  • Concerning the 8-crystal modules we need to make sure that crystals do not change position in the endcap while renumbering/rearranging crystal labeling. The individual crystal position is radiation hardness driven!
  • Question to KVI: Are there more detailed step drawings of the 8-crystal submodules?
  • Concerning the installation in Juelich: Is the KVI mountimg tool adapter still available? (Will ask Rick)

SADC crates:

  • Finaliziation of design needs complete knowledge of back plane PCB design (waiting for Pawel to finish)

-- ThomasHeld - 26 Oct 2018
Topic revision: r1 - 2018-10-26, ThomasHeld
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Panda Wiki Send feedback | Imprint | Privacy Policy (in German)