Minutes of the forward endcap EMC eZuce SRN meeting, 27th of August 2018, 14:00-14:20
Presence:
Basel: -
Bochum: Cathrina, Claudius, Fritz-Herbert, Malte, Matthias, Miriam, Tobias H.
Bonn: Christoph
Groningen: -
Stockholm: -
Uppsala: Pawel
Giessen: -
GSI: -
VPTT Submodule Production:
Bochum is missing an ok to replace broken VPTT. Crystal is sitting ready to be glued and holds production.
Christoph will check the magnetic field measurements and will specify VPTTs to be used instead. (Deadline: This evening/early tomorrow morning).
In the future he will provide a full list, such that Bochum can choose a replacement directly.
Five submodules will be sent tomorrow monring to Bonn, one will be shipped back.
Module 2-x4y2 #4 was transported already by Tom to Bonn.
SADC / Concentrator Status:
All SADCs are produced. Some are still to be tested.Very few boards with problems, repairs to be done. The fibre connectors of all boards will also be tested.
The data concentrator design is finished. The PCB design is submitted and Pawel is awaiting an offer.
No news on crate backplane due to vacation time.
VPTT submodule cosmics test:
One module was measured in 3 positions: Results ok.
Another module was measured several times in all positions. Still checking differences in data.
Results of the cosmics tests of the submodules will be shown at the next meeting.
After meeting question: Will the cosmics results be put into the endcap production database? Is this already done?