APD preamps:
The test setup with a free running cosmics measurement on a vertically suspeded crystals with APD readout gives hard to interprete results due to the absence of a clear visible peak in the resultung cosmics spectrum
We agreed to bring the crystal - mounted to a subunit - to Bonn as there is the setup specifically designed for these measurements with the ability of triggering cosmics fully passing the crystal length, resulting in a more prominent peak
We will try to prepare the subunit and bring it on Friday or Monday to Bonn
For the time being we expect the necessary preamp gain for APD readout to be about three times lower than tested so far (~0.1 V/pC), estimated from beam data and comparison to VPTT readout
Werner will prepare four preamps with this extremely low gain and send it to Bochum for testing - he already tested this version in Basel and achieved stable performance
We try to test this preamps before the June-Meeting at GSI
Malte suspects the general ringing/oscillation problem of the APD preamps being influenced by the grounding scheme
In this context there was some confusion about the grounding layout of the different ISEG HV power suppliy versions: the 16 channel units are not channel wise floating as the 8 channel and VPTT units but have a floating ground common to all 16 channels!
Delivery of the VPTT preamps is delayed by about four weeks. They are expected to arrive end of June.
Read out electronics:
There was some discussion about the definition of thresholds:
Malte and Matthias remarked that the effective threshold is not the stated threshold as there are additional requirements to be fulfilled, i.e. a time over threshold constraint, before accepting a signal, effectively increasing threshold
Myroslav explained that the difference in thresholds is not that dramatic
He will report on the triggering mechanism in the KVI-firmware in detail on the upcoming GSI-Meeting in June
The four shaper versions have been tested:
There is a ringing in the high gain branches causing double peaking spectra
The factor between high and low gain branch is clearly lower than 16
The absolute gains of the branches are not properly adopted to our needs (2 V preamp output to 1 V (?) ADC input)
Linearity test with six different amplitudes done (okay)
Malte will prepare a brief report on this measurements and send it around
HV regulation:
Christoph presented some slides showing the integration of the HV regulation board to the patch panel board (sitting on top as piggy back board)
The HV regulation boards also acts as security lock for the signal U.FL connectors
A mock-up for installation feasibility test may be available the week after next week