Minutes of the Forward Endcap EMC Vibe/eZuce meeting, 4th of October 2021, 14:00-15:15

Time Schedule FWEC:

  • Current cosmics precalibration throughput: 5 submodules in 2 weeks (as is the current maximum submodule production rate), might be increased as submodule production rate increases
  • Gluing of inserts into carbon alveole of successfully tested submodules: 2 a day. Amost all VPTT submodules glued so far, those are the ones mounted to the backplane first.
  • Production of distribution boards is expected to last 4-5 weeks (fitting with components done in Bonn)

HV Rack Connector Boxes:

  • SHV plugs on blue cables coming from the detector would be useful as the extension cables from the racks to the e-hut in Darmstadt would then not be needed to be installed and stored in Jülich

SADC Crates:

  • Outer cooling flanges for the crates still to be delivered
  • Pawel will send backplane PCBs (6- and 15-SADC versions) for final Bonn cable length determination measurements

-- ThomasHeld - 07 Oct 2021
Topic revision: r2 - 25 Nov 2021, ThomasHeld
 
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding PANDA Wiki? Send feedback
Imprint (in German)
Privacy Policy (in German)