Minutes of the forward endcap EMC eZuce SRN meeting, 22th of May 2017, 14:00-14:20

Presence:

  • Basel: Werner
  • Bochum: Claudius, Fritz-Herbert, Matthias, Malte, Miriam, Tobias T.,Tom
  • Bonn: Christoph
  • Groningen: -
  • Stockholm: -
  • Uppsala: -
  • Giessen: excused
  • GSI: -

Signal cabling:

  • Discussion about differences in cable length as guessed by Christoph and Claudius, respectively
  • Difference comes from unclear situation with the SADC connection and some different safety margins taken into account
  • Need to talk to Myroslav (cooling details of SADC crates) and Pawel (detailes about SADC-signal cable connections) via mail

APD preamps:

  • Start of delivery slightly delayed, expected to begin in June - does not interfere with our time schedule
-- ThomasHeld - 31 May 2017

This topic: EMC > WebHome > ForwardEndcapMeetings > Minutes2017-05-22
Topic revision: 2017-05-31, ThomasHeld
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Panda Wiki Send feedback | Imprint | Privacy Policy (in German)