Minutes of the forward endcap EMC eZuce SRN meeting, 22th of May 2017, 14:00-14:20

Presence:

  • Basel: Werner
  • Bochum: Claudius, Fritz-Herbert, Matthias, Malte, Miriam, Tobias T.,Tom
  • Bonn: Christoph
  • Groningen: -
  • Stockholm: -
  • Uppsala: -
  • Giessen: excused
  • GSI: -

Signal cabling:

  • Discussion about differences in cable length as guessed by Christoph and Claudius, respectively
  • Difference comes from unclear situation with the SADC connection and some different safety margins taken into account
  • Need to talk to Myroslav (cooling details of SADC crates) and Pawel (detailes about SADC-signal cable connections) via mail

APD preamps:

  • Start of delivery slightly delayed, expected to begin in June - does not interfere with our time schedule
-- ThomasHeld - 31 May 2017
Topic revision: r1 - 31 May 2017, ThomasHeld
 
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding PANDA Wiki? Send feedback
Imprint (in German)
Privacy Policy (in German)