  • Evironment requirements like temperature, humidity Evironment requirements like temperature, humidity:
    • during installation
    • during operation
    We assume that the target hall is climatized to room temperature and humidity is controlled to prevent dew.
    • during installation: no special requirements
    • during operation: no special requirements
  • Maintainance
    • How often the subdetector will be accessed, every downtime, never? There are no regular disassembling procedures necessary, however in case of problems, eg. dead PMT on radiator end (TOP project option), a procedure is needed, see below.
    • How you plan to replace parts: After disconnecting obstacles like the target pipe and eventually water tank, the DIRC will be retracted backwards from the detector together with the subsystems inside the DIRC and dismantelled in the upstream region of the solenoid.
  • Maintainance Space:
    • How often the subdetector will be accessed, every downtime, never? Storage: replacement parts need minor space, say 10-20 m2.
    • How you plan to replace parts. Mounting area:
    1. m2 labspace, time ???
    • Electronics: BaBar option need 7000 channels: customized ASIC solution like the GSI-Taquila project.
    • Utilities (cooling machines...): The BaBar option needs an H2O purifier system close to the water tank. 10-20 m2 ???
  • Space Resources
    • Storage purifiers: Above mentioned H2O purifier.
    • Mounting area cooler: None
    • Electronics supply lines: N2 for dustfree, dry operation (???)
    • Utilities (cooling what else? machines...)
  • Resources Cables: the area of cables leaving the detector is enough for the moment. So, how many squaremeters cable area you need.
    • purifiers
    • cooler
    • supply lines
    • what else?
    BaBar option: PMT array is outside of solenoid. TOP option: 200 channels are about 800 mm2 which have to leave the solenoid. In case of the 3d DIRC the many pixels require sparsification scheme (Chip readout) and might have similar requirements.
  • Cables: Support the area of cables leaving the detector is enough for the moment. So, how many squaremeters cable area you need.
    • Weight of detector: Bars=200*180*3.5*1.7*cm3*2.2g/cm3=500kg, aluminium support=500kg, water tank=4000kg, SUM=5000kg
    • Support ideas: BaBar uses a gusset with should add additional 1000kg
    • Support points: The gusset.
    • Veto areas, where other subsystems are forbidden to connect to: Nothing special.
  • Support Alignment:
    • Weight of detector.
    • Support ideas.
    • Support points.
    • Veto areas, where other subsystems are forbidden to connect to.
    Optical and mechanical.
  • Alignment

-- CarstenSchwarz - 29 Jun 2006

View topic | View difference side by side | History: r3 < r2 < r1 | More topic actions
 
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding PANDA Wiki? Send feedback
Imprint (in German)
Privacy Policy (in German)