Still no final green light for the storage room for the cooling components...
The light pulser module in Bonn currently shows an intensity spread of <2% while it was way more in the past (~5%). The reason is not yet clear.
Calibration of the large (for 16 crystal submodules) HV boards has been started, throughput is about 23 h per board, corresponding to 5-6 per week.
The whole pile of boards therefore will be finally measured not before early 2027
--