Minutes of the Forward Endcap EMC Meeting, 26th of May 2025, 14:00 - 14:20
There are still five submodules sitting in Bochum, waiting for completion/repair
Bonn colleagues are in need of cables currently located in Bochum:
Flat cables (
THMPs
)
Screened black LV cables
Blue HV cables
Lukas: light blue optical network cables and SFP cages will be brought to BN next week
The thyristor boxes for the coolant heaters are still sitting in Bochum
More finished submodules will be delivered to Bonn next week (presumably)
--